11/5/19 - The project begins.
11/12/19 - The hull seams are filled with epoxy.
11/13/19 - Rudder trunk pieces are fiberglassed.
Skeg wormshoe is epoxied in place.
The spars are epoxied to full length.
11/16/19 - The first seal coat of epoxy is applied to the hull.
11/17/19 - The second seal coat is applied.
11/20/19 - The hull is partially sanded.
The hull is sanded and ready for primer.
11/24/19 - A PVC tow eye is installed.
11/25/19 - The first coat of primer is sanded.
Second coat of primer is applied.
PVC is trimmed and sanded.
11/26/19 - The primer is sanded.
11/27/19 - The first coat of paint is appiled.
12/1/19 - The second coat of paint is on.
12/3/19 - The spars are sanded.
Four coats of paint are applied.
12/5/19 - Work on the interior begins!
One seal coat of epoxy is applied.
Two seal coats of epoxy.
12/6/19 - The first seal coat of epoxy is applied to the spars.
Foils are fiberglassed.
Mahogany footbraces are sealed with epoxy.
12/10/19 - Seal coats of epoxy are applied.
Final seal coat of epoxy is applied to the spars.
Spacers for rudder gudgeons are epoxied in place.
The rudder is test mounted.
3/11/20 - The underside of the seat/bulkhead joint is filletted.
3/12/20 - The final coat of paint is applied to the hull.
3/14/20 - The foils are sanded.
3/17/20 - The interior is half sanded.
Sanding of the interior is complete.
3/18/20 - The interior is washed.
The interior is taped off in preparation for primer.
3/19/20 - The first coat of primer is applied to the interior.
3/20/20 - The first coat of paint is applied.
3/23/20 - Second coat of paint is applied.
3/24/20 - The final coat of paint is applied.
3/25/20 - The tape is removed and the boat is ready for varnish.
3/26/20 - The first coat of varnish is applied to the seats and bulkheads.
The spars get a coat of varnish.
Rudder and daggerboard are varnished.
3/27/20 - Two more coats of varnish have been applied.
4/1/20 - Footbraces are epoxied in place.
Major construction is complete!
Hardware is installed on mast.
4/2/20 - The boat is moved outside to allow for rigging the sail.
The sail is fit to the spars.
The sail rig is set up.
The rudder is hung on the stern.