8/15/19 - The panels are laid out.
-
The panels are epoxied together.
-
8/16/19 - The flipside of the panels are epoxied together.
-
The first two panels are wired together.
-
8/17/19 - The hull is close to being fully wired.
-
8/18/19 - The hull is fully wired.
-
8/19/19 - The seams are filled with thickened epoxy.
-
8/20/19 - The seams on the other side are filled with epoxy.
-
8/26/19 - The inside seams between hull planks are filled with thickened epoxy.
-
Fiberglass cloth is laid out on the hull interior.
-
The cloth is saturated with epoxy.
-
The bulkheads are fiberglassed.
-
The cockpit panel is epoxied together.
-
Excess cloth is trimmed.
-
8/27/19 - The recessed deck fittings are cut out.
-
The deck is mostly wired together.
-
The deck is fully wired together.
-
The seams are filled with thickened epoxy.
-
8/29/19 - Fiberglass tape is laid out on the underside of the deck.
-
The underside of the deck is ready for epoxy.
-
The fiberglass and wood are saturated with epoxy.
-
Footbrace studs are epoxied in place.
-
Gaps in the deck seams are filled with epoxy.
-
Gaps in the hull seams are filled with epoxy.
-
8/30/19 - The recessed deck fittings are epoxied in place.
-
The deck is epoxied to the hull.
-
Bulkheads are fiberglassed.
-
The inside of the sheer joint is epoxied.
-
Hatch parts and coaming lips are fiberglassed.
-
8/31/19 - The inside of the sheer joint is epoxied.
-
9/1/19 - The hull is sanded smooth.
-
Fiberglass cloth is laid out on the hull.
-
The fiberglass is saturated with epoxy.
-
9/2/19 - Glass tape is laid along the keel.
-
The first fill coat of epoxy is applied.
-
Second fill coat.
-
9/3/19 - The deck is fiberglassed.
-
First fill coat is applied to the deck.
-
Second fill coat.
-
9/4/19 - The coaming riser is epoxied in place.
-
The myrtle coaming lip is epoxied in place.
-
The coaming lip is fiberglassed.
-
The glass is saturated.
-
Excess cloth is trimmed.
-
The coaming and deck are given a fill coat of epoxy.
-
9/9/19 - The hatches are cut out.
-
Hatch lips are epoxied together.
-
9/10/19 - The aft hatch lips are epoxied in place.
-
Coaming is cleaned up and sealed with epoxy.
-
Aft bulkhead is installed.
-
Forward hatch lip is installed.
-
The clamps are removed.
-
9/21/19 - The entire boat has been sanded.
-
9/22/19 - The boat is washed and ready for varnish.
-
The first coat of varnish is applied.
-
10/7/19 - Strapless hatch toggles are sealed with epoxy.
-
10/23/19 - The hatch gaskets are glued in place and the deck rigging is installed.
-
Strapless hatch system is installed.