8/12/21 - The boat as it was at the end of class.
The inside sheer joint is filled with epoxy and reinforced with fiberglass tape.
8/17/21 - The hull is given two fill coats of epoxy.
10/1/21 - Footbrace studs are installed.
10/4/21 - The coaming is ready for fiberglass.
The glass is saturated with epoxy.
10/11/21 - The deck is given the first fill coat of epoxy.
10/15/21 - The hull is half sanded.
10/20/21 - Several coats of varnish have been applied to the hull.
10/21/21 - The deck is given first coat of varnish.
10/23/21 - Several more coats of varnish have been applied.