6/24/24 - Work is started on the latest student boat.
6/25/24 - Fillets and fiberglass tape are installed on the bottom hull/seat joint.
6/27/24 - Hole for an access hatch is cut in the deck.
6/28/24 - The hole is reinforced.
7/1/24 - The rail to hull joint is filleted.
The transom is fiberglassed and the entire hull is given a fill coat of epoxy.
7/5/24 - A hole for tying a rope is drilled.
7/8/24 - The hull is partially sanded in preparation for paint.
7/9/24 - Sanding is complete.
First coat of primer is applied.
Movable seat thwarts are fiberglassed.
7/13/24 - The primer is sanded.
First coat of paint is applied.
7/14/24 - Second coat of paint.
7/24/24 - The interior is epoxy sealed.
7/31/24 - The lower cockpit is primed.
8/19/24 - The first coat of paint is applied.
8/20/24 - The second coat of paint is applied to the interior.
8/21/24 - Final coat of paint.
8/23/24 - First coat of varnish.